Church
New carpet, new lighting, renovate south wall (behind the altar) and new choir platform
September 10
The shelf has been placed behind the altar.


Stained gass above the new door has been complete.

September 2
Tiling is complete behind the altar, the tabernacle and cross have been installed.

Holy water fonts have been replated and reinstalled.

August 25
Tile work behind the altar is almost complete.

New baptismal font has been installed.

New door has been installed and stainglass has been put in.

Kneelers have been installed.

August 18
Pews have been reinstalled.

August 5
Carpet is going in.

Hardwood is being laid in the chior area.

July 29
Lighting installation is complete.

July 24
Panels have been placed on the wall behind the altar.

July 9
Opening is cut for the door on the south wall of the church.


Second HVAC unit has been placed.

July 7
Lights have passed electrical inspection, drywall is being installed in preparation for taping and mudding.


The second HVAC unit has been removed (from behind the cry room).

July 1
Lights are being installed.


June 27
The tiered floor for the choir has been poured.


June 21
Old lighting has been removed.

June 13
The carpet has been removed.

June 8
The tile has been removed from the south wall.

June 3
The pews have been removed and everything is ready to begin!