Narthex

Update bathrooms, open up ushers closet, add cabinets and digital display

September 10

Resurrection Chapel is complete.

Communications area is set up.

Furniture has returned.

September 2

Tiling is complete in the Resurrection Chapel (former ushers closet).

Communications area is complete and the digital display has been setup.

New carpet has been installed.

August 25

Communications area cabinets and counters have been installed.

August 19

Bathrooms are complete.

August 12

Cabinets are set for the media wall.

Cabinets are set under the existing counter.

Bathroom fixtures have been installed and tiling started.

July 24

Dry wall complete in the cry room.

Second bathroom has been dry walled.

Dry wall has been complete on the opening of the former usher's closet.  Lights are being wired.

The data wall has been dry walled.

July 13

Wall has been closed in following the placement of the second HVAC unit.

Dry wall has been completed following lighting updates.

Wiring in data wall is underway.

July 7

Wiring is ongoing for lighting.

First bathroom has been drywalled.

July 1

Usher's closet has been opened up.

June 21

Framing for cabint and digital display wall is complete.

June 13

Bathrooms have been gutted.