Sacristy 

New HVAC and new cabinets

September 2

The sacristy has been repopulated.

August 25

Cabinets and counters install has been completed.

August 19

Data cabinet (containing sound, streaming and bell equipment) has been returned.

August 3

New cabinets have been placed.

Lighting controls are installed.

July 29

Wiring for lighting controls is ongoing.

July 24

Wall has been closed in following the HVAC work and the doorway has been replaced.

June 21

Sacistry cabinets have been removed, maintence closet wall temporarily opend up and the new HVAC is being installed.

June 8

The sacistry has been emptied and the sound system / data cabinet has been removed.